Project: I-CAVS   -  
            Listing of Entries
    (Please mouse-over any icon to get a description of that function).



Categories
  
Builder Name:paolo cavosi   -  
Project:   Vans - RV-10
Total Hours:2429.2
Total Flight Time:
Start/Last Date:May 28, 2019 - No Finish Date
Engine:IO-540 Thunderbolt Serial # EL-38135-48E
Propeller:MT Propeller MTV-12-B/193-53 serial 22G1268-K
Panel:Garmin G3X
 
Friendly URL: https://eaabuilderslog.org?s=I-CAVS

Home or Last Project Picture

Nov 14, 2021     11-7 Empennage Attach Step 1-9 - (2.5 hours)       Category: Fuselage
Prepared the template for the bell crank assembly neutral position. Adapted the length of the F-1091 Elevator pushrod according to the template and elevator in neutral position.
Checked both rod ends bearings have over half the thread engaged making it impossible for a bearing to back off the pushrod if both ends are pinned.
Inserted the MD3614M rod end bearings and fastened with jam nuts to 3/4".
Bolted the rudder to the vertical stabilizer starting with top hinge, then the bottom hinge and finally the middle hinge. Alignment was good. Checked the 35�th sides. Distance measured from the trim inboard angle to the rudder (perpendicular measure) is 2 inches, resulting in an estimated deflection >35��Slightly adjusted the bottom bearing, deflection is still over 35��n the recommended minimum Lucio and I agreed to consider this acceptable.


 


NOTE: This information is strictly used for the EAA Builders Log project within the EAA organization.     -     Policy     -     © Copyright 2024 Brevard Web Pro, Inc.